Melter Costs and Savings by Plant - Commercial Glass Division

(In $ Millions—over an 8-year period)
LIGHTING PRODUCTS
(Joplin, MO)
New Installation Modifications to Existing Melters
New Gas Furnace All-Elec. Melter 100% Oxy Melter Oxygen Boosting Electric Boosting
Acquisition Costs 30.4 20.9 26.6 5.7 3.8
Pollution Control (Savings) (6.08) (3.8) (3.88) (4.18)
Energy Penalty 15.96 7.6 5.89 11.78
Net Cost   30.4 30.78 30.4 7.71 11.4

FLAT GLASS
(Cairo, IL)
New Installation Modifications to Existing Melters
New Gas Furnace All-Elec. Melter 100% Oxy Melter Oxygen Boosting Electric Boosting
Acquisition Costs 45.6 31.4 39.9 8.55 5.7
Pollution Control (Savings) (9.12) (5.7) (5.81) (6.27)
Energy Penalty 23.94 11.4 8.84 17.67
Net Cost   45.6 46.22 45.6 11.58 17.1